(april 11, 2005)
Glueing of the heaters and insulation on the outer surface of the vessel.
(april 8, 2005)
Vessel arrived at Nikhef
(april 6, 2005)
Thermo have finally completed the vessel. Vacuum tests achieved a pressure of 6.10-10 Torr.
(march 9, 2005)
Machining of the dummy beam pipe (in case of a emergency) at the Free University of Amsterdam (VU).
(febr 25, 2005)
(feb 9, 2005)
(jan 12, 2005)
Milling of the holes.
(december 23, 2004)
The vacuum vessel welded and placed on the milling machine. Underestimated are the planed working hours and the shrink during welding. This shrink means that the vessel at some points in total length, before final machining, already 4 mm to short is. Thermo need 6 weeks for delivering (delivery 1/2 february).
The aluminium welding is subcontracted at Perfect Fusion (2 Bels Forstall, Cottages Faversham; Kent)
(november 11, 2004)
The vacuum vessel is in production at Thermo electron corporation located in Hastings (UK).