More pictures Left Detector see: Production Left Detector
(january 9, 2007)
About 60 groundsprings (goldplated CuBe) are bended.
(october 11, 2006)
Jaap stolte soldered all heater and PT100's to the two electronic boards.
(october 5, 2006)
The cables are routed and fixed with aluminium clips.
(august 25, 2006)
PT100 temperature sensors and glued.
(june 30, 2006)
All 2 kapton WATLOW heaters are glued at the inside with araldite 2011.
(june 19, 2006)
3D measuring by Berend Munneke is done. Measuring results : PDF, hpgl
(may 31, 2006)
Machining of the grooves and dowelpin holes are done.
(may 19, 2006)
The two parts are cleaned, glued and pinned together. Johan Kos is machining the top surface at NIKHEF.
(may 11, 2006)
Premachining is finished at the VU and will be final machined at NIKHEF.
(may 3, 2006)
Premachining at the VU (Free University of Amsterdam) is almost ready.
LINKS TO RELATED SITES
  • Production Left Detector
  • Production Left C02 Cooling evaporator
  • Production Right Detector
  • Production Right C02 Cooling evaporator
  • Production C02 Cooling system
  • 3D DESIGN MODULE SUPPORT
  • 3D DESIGN DETECTOR
  • Drawings in PDF Format
  • HPGL drawings of the modules support mechanics in EDMS/CDD
  • HPGL drawings of general assembly views in EDMS/CDD