(february 26, 2007)
The first modules are placed and the Right detector comes back from the 3D measurement.
(18 and 19 january, 2007)
Installation test of the leftdetector at IP8
(15/16/19 january, 2007)
Transport test of the leftdetector at IP8
See here for the measurement results
(January 10, 2007)
The Detector is transported to CERN
(January 8, 2007)
(January 3-5, 2007)
Installation of all the VELO cables at NIKHEF is successfully. After installation tests are done with the resistant measurement system from CERN and all cables are okay [results]. We discovered at two feedthroughflanges rotated connections.
Numbering of the cables: [Right detector] [Left detector]
(December 20, 2006)
Jan Koopstra is testing all resistance of the flatcables with a setup from CERN.
(November 27, 2006)
For the coolingtest the detector is placed in horizontal position and evacuated.
(November 13, 2006)
Installation of the Pile-up cables at NIKHEF.
During installation one cable (part 3 of cable no. 19191) was damaged but electrical gives no problems and we isolate it with epoxy.
(November 10, 2006)
On all PILE-UP cables are connection-bars glued. There are 35 VELO cables and 18 PILE-UP cables ready.
PILE-UP
Type A
PILE-UP
Type B
(November 2, 2006)
On 16 of the VELO cables are connection-bars glued. There are now at Nikhef 35 VELO cables (in total we need 52 VELO cables for one detector).
(November 1, 2006)
The detector is almost ready for the coolingtest. The heaters are soldered and routed by Erno Roeland.
In the coolingsetup is a accumulator added by Peter Thobe.
(oktober 26, 2006)
Succesfully assembly of the left detector.
(oktober 25, 2006)
Succesfully installation of the evaporator into the 'Module Support'.