(januari 20-22, 2010)
Maintenance at the coolingplant by Gertan Mul, Erno Roeland en Martijn van Overbeek.
|
(jan 15, 2008)
Modifications on the coolingplant
|
(july 6 - august 9, 2007)
The installation of the coolingplant in the PIT.
|
(june 15, 2007)
The coolingplant arrived at CERN.
|
(june 6, 2007)
The coolingbridge is placed in the back of the VELO and connected to the transferlines
|
(june 3-6, 2007)
The coolingtest was succesfull and a cooling-party was given to celebrate the transport of the coolingplant to CERN.
|
(june 20, 2007)
A high pressure capillary glass
|
(may 11, 2007)
|
(may 10, 2007)
Peter Thobe and Martin Doets are making removable isolation parts for the C02 pumps
to have create a 'easy' maintaining access.
|
(march 1 - april 16, 2007)
Pictures of the the C02 and Freon system.
|
(february 22, 2007)
Cabling of the C02 system is finished.
|
(februari 1, 2007)
|
(december 20, 2006)
Cabling is almost finisched by Peter Thobe and Jaap Stolte.
|
(november27, 2006)
|
(ovember 15, 2006)
The C02 system is cleaned and assembly is started in the vacuumlab at NIKHEF.
|
(oktober 25, 2006)
Joop Rovekamp made a coolingplate for the backup C02 pump.
|
(oktober 12, 2006)
Almost all orbital welds are done and a cable rack is mounted on top.
|
(oktober 5, 2006)
Martin and Erno already made about 200 successfully orbital weldings in the CO2 cooling system.
|
(september 17, 2006)
A start of welding all stainless steel tubes is made with
the new 'orobital welding apparatus' for Swagelock.
|
(august 28, 2006)
The main welds of the three accumulators are welded and radiographic examined at
Hoefnagel & Meijn BV in the Netherlands:
Raport 1
,Raport 2
Pressure tests are done at RUSH ARMADAC BV CALIBRATION LABORATORY (R.A.C.L.) in the Netherlands at 170 Bar according
CODAP norm.:
Pressure Test Raport
|
(august 17, 2006)
The 3 accumulators are assembled (welding is done by Rob Leguyt) and ready for welding at the biq spheres.
|
(july 26, 2006)
Rob Leguyt is welding the heaterhousing of the accumulator.
|
(july 23, 2006)
The three LEWA C02 pumps arrived at NIKHEF.
|
(july 20, 2006)
Martin Doets is building the first parts into the 'cooling rack'. All piping will be
temporary 'connected' with plastic tubes and finally welded with a 'orbital welding machine'.
|
(june 30, 2006)
The accumulator top- and bottom-spheres and tubes are ready for welding.
Assembly of the baseplate is started.
Reinforced plates for a new 'high pressure' heat exchanger from
SWEP
are ready. Dimitry is milling the connecting holes into one plate,
and Martin re-threaded four fittings of Swagelock.
|
(june 8, 2006)
The first prototype of the valve 'extender' is ready.
|
(june 8, 2006)
5 (3 are necessary) coils of the acummulator are succesfully made.
|
(may 31, 2006)
The first coil of the acummulator.
|
LINKS TO RELATED SITES |
Drawings (PDF):
Accumulator Drawings
All Cooling Drawings
Production status Right C02 Evaporator
Production status Left C02 Evaporator
|