Relevant information:
  • Capillary in the Manifold
  • Cable numbers in the Right Detector
  • (august 28,, 2011)
    A damaged cooling cookie is removed and replaced bij Erno Roeland and Dimitri John at CERN.
      damaged
      repaired
    (june 14,, 2011)
    The Left (A side) Replacement Detector is arrived CERN.
    (june 6, 2011)
    The Left (A side) Replacement Detector is on transport to CERN.
    (june 1,, 2011)
    The Left (A side) Replacement Detector is ready for transport to CERN.
    (may 18,, 2011)
    The Left (A side) Replacement Detector is almost ready for transport to CERN.
    (march 31, 2011)
    On march 30 the installation of the first cables sets are started.
    (february 14, 2011)
    The Right Replacement Detector is placed in the cleanroom at CERN (building 68) by Raphael Dumps.
    (february 4, 2011)
    The Right Replacement Detector is put on transport by 'Van der Wal Transport BV' to CERN.
    (february 1, 2011)
    Champagne Party to celebrate the transport of the Right Replacement Detector.
    (january 27, 2011)
    The Right Replacement Detector is ready for transport to LHCb.
    (january 13, 2011)
    The last 2 cable sets (Pile-Up) are installed in the Right Replacement Detector.
    (january 7, 2011)
    The first 6 Cable Sets are succesfully installed in the Right Replacement Detector.
    (december 9, 2010)
    Machining 'in place' of a forgotten pocket on the module support
    (november 19, 2010)
    Preparations are started for the coolingtest on the horizontal Left Detector.
    (november 18, 2010)
    5 type VELO A and 3 type VELO B are ready for installation into the right detector.
    (november 09, 2010)
    The coolingtests are started on the horizontal Right Detector.
    (november 03, 2010)
    The Right Detector is rotated on a frame for the horizontal coolingtests.
    (oktober 18, 2010)
    Left Detector: Piet de Groen is re-soldering the right slow control prints (with female print connector). Two long kapton cables are connected to the feedthrough flanges for PT100 readouts.
    (oktober 7, 2010)
    Assembly of the Left Module support, Evaporator and Hood is ready.
    (september 30, 2010)
    Assembly of the Left Evaporator and Module support is ready.
    (september 28, 2010)
    The left cooling evaporator is ready to assemble with the left module support.
    (september 7, 2010)
    Left Module Support.
    (august 4, 2010)
    The Right detector is under vacuum 'waiting to be cooltested'.
    (july 30, 2010)
    The right detector Hood is assembled with the Right CO2 evaporator and Module base. The assembly is placed in the cooling lab for preparing the CO2 tests. On each cooling pad heating block a temperature switch (Clickson) is mounted. The Clickson switches the cooling pad off at 110 degrees celcius. There are 5 heaters (56 Ohm each) serial connected.
    (july 1, 2010)
    Left module support. The Left and Right detector Hood and Trolley are ready.
      Gluing of the supportstrip on the long-flatcables:
    (may 4, 2010)
      Soldering of the slow control prints:
    (april 26, 2010)
      All PT100 are replaced by 4 wireded ones. Rerooting is also done to get a smoother result.
      Gluing of the aluminum mounting strips on the double pair of kapton cables are an ongoing job.
    (april 14, 2010)
      Left Module support is cleaned and placed in the cleanroom.
      Piet de Groen is soldering the PT100 temp sensors en Watlow heaters on the inside of the Right module support.
    (april 4-13, 2010)
    All Watlow kapton heaters and PT100 temperature sensors are glued inside the right module base
    (march 11, 2010)
    Half of the cleanroom (H070; formerly the ATLAS BOL cleanroom) is cleared and available for building up and vacuum testing of the two replacement detectors.
    Almost all parts are machined. 20 coolingpads are flow checked (at a pressure difference of 1 bar) and pressure checked at 170 bar. Both detector hoods are leak tested.
    LINKS TO RELATED SITES