(february 26, 2007)
The first modules are placed and the Right detector comes back from the 3D measurement.
|
(18 and 19 january, 2007)
Installation test of the leftdetector at IP8
|
(15/16/19 january, 2007)
Transport test of the leftdetector at IP8
See here for the measurement results
|
(January 10, 2007)
The Detector is transported to CERN
|
(January 8, 2007)
|
(January 3-5, 2007)
Installation of all the VELO cables at NIKHEF is successfully. After installation tests are done with the resistant
measurement system from CERN and all cables are okay [results]. We discovered at two feedthroughflanges
rotated connections.
Numbering of the cables:
[Right detector]
[Left detector]
|
(December 20, 2006)
Jan Koopstra is testing all resistance of the flatcables with a setup from CERN.
|
(November 27, 2006)
For the coolingtest the detector is placed in horizontal position
and evacuated.
|
(November 13, 2006)
Installation of the Pile-up cables at NIKHEF. During installation one cable (part 3 of
cable no. 19191) was damaged but electrical gives no problems and we isolate it with epoxy.
|
(November 10, 2006)
On all PILE-UP cables are connection-bars glued. There are 35 VELO cables and 18 PILE-UP cables
ready.
PILE-UP Type A |
|
|
|
|
|
PILE-UP Type B |
|
|
(November 2, 2006)
On 16 of the VELO cables are connection-bars glued. There are now at Nikhef
35 VELO cables (in total we need 52 VELO cables for one detector).
|
(November 1, 2006)
The detector is almost ready for the coolingtest. The heaters are
soldered and routed by Erno Roeland.
In the coolingsetup is a accumulator
added by Peter Thobe.
|
(oktober 26, 2006)
Succesfully assembly of the left detector.
|
(oktober 25, 2006)
Succesfully installation of the evaporator into the 'Module Support'.
|
LINKS TO RELATED SITES |
3D DESIGN Detector
3D DESIGN Module Support
3D DESIGN CO2 Coolingstytem
Production LEFT Module Support
Production LEFT C02 Cooling
|