| Status of module-to-disc work at NIKHEF | ||||||||||||
| ID | Task | Time est. (days) | Amount of work completed (days) | |||||||||
| 9A | 8A | 7A | 6A | 5A | 4A | 3A | 2A | 1A | ||||
| 1 | Mount dummy modules | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | |
| 2 | Connect in testbox | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 0 | |
| 3 | Test services | 5 | 5 | 5 | 5 | 5 | 5 | 5 | 0 | 5 | 0 | |
| 4 | CMM | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 0 | |
| 5 | Mount Lowers | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 0 | 3 | 0 | |
| 6 | Connect in testbox | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 0 | |
| 7 | Test lowers | 5 | 5 | 5 | 5 | 5 | 5 | 5 | 0 | 5 | 0 | |
| 8 | Mount uppers | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 0 | 3 | 0 | |
| 9 | Connect in testbox | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 0 | |
| 10 | Test all | 5 | 5 | 5 | 5 | 5 | 5 | 5 | 0 | 4 | 0 | |
| Per centage finished | 78 | 100 | 100 | 100 | 100 | 100 | 100 | 4 | 96 | 0 | ||
| Date | Patrick's planning, v2.5 | NIKHEF Progress | |||||||||
| 01/05/05 | 0 | 0 | |||||||||
| 24/6/05 | 11 | 8 | |||||||||
| 08/07/05 | 22 | 22 | |||||||||
| 15/07/05 | 26 | 26 | |||||||||
| 29/7/05 | 33 | 31 | |||||||||
| 12/08/05 | 44 | 37 | |||||||||
| 26/08/05 | 56 | 42 | |||||||||
| 20/09/05 | 63 | 52 | |||||||||
| 14/10/05 | 78 | 63 | |||||||||
| 28/10/05 | 89 | 68 | |||||||||
| 11/11/05 | 100 | 73 | |||||||||
| 28/11/05 | 100 | 78 | |||||||||
|
|||||||||||