(Date: 09/12/'05) Total Disk 9A Disk 8A Disk 7A Disk 6A Disk 5A Disk 4A Disk 3A Disk 2A Disk 1A
  Task Name % Finished                  
                                         
  Finishing Dates   17-Jun-05 20-May-05 24-Jun-05 5-Aug-05 26-Aug-05 7-Oct-05 25-Nov-05 1-Jul-05 16-Dec-05
                                         
  Pre Assembly                                      
1 Grounding and Shielding Foils 100 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
2 DCS Phase 1 100 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 FSI Phase 1 100 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
                                         
  Assembly Phase 2                                      
4 Wiggly Tapes 100 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
5 Outer Cooling Circuits 100 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 HO Fibre Harnesses 100 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
7 Inner Cooling Circuits 100             1 1 1 1 1 1 1 1 1 1    
8 HI Fibre Harness 92             5 5 5 5 5 5 5 3 5 5    
9 Middle Cooling Circuits 100     1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
10 HM Fibre Harnesses 100     5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
11 FSI Phase 2 100 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
12 Bond All Clips 100 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
13 Testing Wiggly Tapes 89 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0
                                         
  Assembly Phase 3                                      
14 Testing Fibre Harnesses 100 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
                                         
  Assembly Phase 4                                      
15 Complete Cooling Circuits 100 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
                                         
  Assembly Phase 5                                      
16 Leak Test, Pressure test and Clean Circuits 100 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
                                         
  Assembly Phase 6                                      
17 DCS Phase 2 100 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 3 3
18 Precise Placement 95 2 2 4 4 4 4 6 6 6 6 6 6 6 4 6 6 4 4
19 Solder Grounding and Shielding Foils 100 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 2 2
20 Repair / Resolder Grounding Fingers 100 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
21 Replace Dummy Hybrids with Dummy Modules 89 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0
                                         
  Final Quality Control                                      
22 Position Measurement & Analysis 89 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 0
23 Final QA/QC 78 5 5 5 5 5 5 5 5 5 5 5 5 5 0 5 5 5 0
24 Final Position Measurement & Analysis 78 3 3 3 3 3 3 3 3 3 3 3 3 3 0 3 3 3 0
                                         
  Assembly Phase 8                                      
25 FSI Phase 3 63 0 0 1 1 1 1 1 1 1 1 1 1 1 0 1 0 1 0
                                         
  Disc Status (Percentage Finished) 95.8   100   100   100   100   100   100   84   99   80
  Aproximate number of working days 661 59   69   69   79   79   79   79   79   69